Las Cruces Public Schools Capital Outlay Projects
2018 Bond Projects
(In Progress)
CESAR CHAVEZ ES SECURE VESTIBULE
CESAR CHAVEZ ES SECURE VESTIBULE
CESAR CHAVEZ ES SECURE VESTIBULE
G. Sandoval Construction
This project will consist of securing the main entrance with a secure vestibule
In Construction
Estimated Completion Date: July 2022
Construction: 75%
Estimated Budget
$62,659
Funding Source
Bond/PSCOC
COLUMBIA ELEMENTARY SCHOOL
COLUMBIA ELEMENTARY SCHOOL
G. Sandoval Construction
This project will consist of demolishing existing facility & building a new school at the same site for 752 students
Purchasing working on Architect’s contract to design the new school
Estimated start date March 2022
Estimated completion of design March 2023
Working with general contractor to obtain permit to start demolition
Estimated start date March 2022
Estimated completion August 2022
Architect awarded contract May 23, 2022, to design the new school
Kick off meeting held May 25, 2022
Demolition is 30% complete
Construction of new school estimated to start May 2023
Construction of new school estimated to be complete August 2024
Estimated design and Demo. Budget
$7,127,115
Funding Source
Bond/PSCOC
DESERT HILLS ES NEW MULTIPURPOSE/KITCHEN & RENOVATION OF EXISTING CAFETERIA
DESERT HILLS ES NEW MULTIPURPOSE/KITCHEN & RENOVATION OF EXISTING CAFETERIA
Huitt-Zollars Inc.
This project will consist of adding a new multipurpose room, kitchen, renovating the old cafeteria into new classroom/administrative space as well as securing the main entrance with a secure vestibule
Scope: increased enrollment to 783 students, to include adding a kinder wing with 5 classrooms & remodeling existing kinder classrooms
Starting Date: April 2020
Architect working on the design phase, 70% complete
Estimated start of construction July 2022
Estimated Completion date: October 2023
Estimated Budget
$11,033,980
Funding Source
Bond/PSCOC
FAIRACRES ELEMENTARY SCHOOL NEW CLASSROOM WING, NEW MULTIPURPOSE/KITCHEN & RENOVATION OF EXISTING CAFETERIA
FAIRACRES ELEMENTARY SCHOOL NEW CLASSROOM WING, NEW MULTIPURPOSE/KITCHEN & RENOVATION OF EXISTING CAFETERIA
AKS/ESA Construction
This project will consist of adding a new multipurpose room, kitchen, renovating the old cafeteria into new classroom/administrative space as well as adding a new classroom wing
Starting Date: December 2020
Working with design professional to revise the drawings
Design complete
Project on hold pending funding
Estimated construction start date June 2022
Estimated construction completion Aug 2023
Estimated Budget
$10,182,400
Funding Source
Bond
HIGHLAND ES SECURE VESTIBULE AND LIGHTING UPGRADES
HIGHLAND ES SECURE VESTIBULE AND LIGHTING UPGRADES
HIGHLAND ES SECURE VESTIBULE AND LIGHTING UPGRADES
Nine Degrees Architecture & Design Inc. / Classic Industries
This project will consist of securing the main entrance with a secure vestibule as well as upgrading the lighting with LED’s
Starting Date: February 2020
Estimated Completion Date: February 2022
Construction: Completed
Estimated Budget
$73,500
Funding Source
Bond/PSCOC
HILLRISE ELEMENTARY SCHOOL NEW MULTIPURPOSE/KITCHEN & RENOVATION OF EXISTING CAFETERIA
HILLRISE ELEMENTARY SCHOOL NEW MULTIPURPOSE/KITCHEN & RENOVATION OF EXISTING CAFETERIA
Vigil & Associates/ ESA Construction
This project will consist of adding a new multipurpose room, kitchen, renovating the old cafeteria into new classroom/administrative space
Progress Report
Starting Date: December 2020
Estimated Completion Date: August 2023
Construction Progress: 50%
Phase 1 work continues – completion of restrooms in progress, re-roof over renovated classrooms in progress
Phase 2 work in progress – footing concrete placement
CMU stem wall construction in progress
Plumbing rough-ins complete
HVAC Upgrades for existing school - design phase complete, working on pricing (Federal Funds)
Interior walls at renovation have been textured and paint work
started
Installation of sprinkler system at renovation
Metal framing in progress
CMU block wall in progress
Portables relocated
Estimated Budget
$8,491,456
Funding Source
Bond
LYNN MS HVAC, SECURE VESTIBULE AND LIGHTING UPGRADE
LYNN MS HVAC, SECURE VESTIBULE AND LIGHTING UPGRADE
AKS Architecture
This project will consist of upgrading the existing HVAC, upgrading the lighting with LED’s as well as securing the main entrance with a secure vestibule
Starting Date: February 2020
Estimated Completion Date: December 2022
Pending GC selection
Estimated Budget
$4,248,260
Funding Source
Bond/PSCOC
LCPS OPERATIONS FACILITY
LCPS OPERATIONS FACILITY
Vigil & Associates
This project will consist of building multiple facilities at the 15-acre lot on Tashiro RD to accommodate Physical Plant, Materials Management, Construction and Food Service’s needs
Starting Date: March 2021
Estimated Completion Date: September 2023
Design complete
Waiting on Purchasing Dept. for advertisement and bid dates for construction
Estimated Budget
$22,250,000
Funding Source
Bond
MACARTHUR ELEMENTARY ADDITION AND RENOVATION OF FRONT OFFICE
MACARTHUR ELEMENTARY ADDITION AND RENOVATION OF FRONT OFFICE
Desert Peak Architects
This project will consist of designing & constructing additional square footage to the current main administrative area to meet PSFA adequacy standards (parent workroom, etc.) This will also include remodeling & expanding the nurse’s area and adding a secure vestibule at the entrance
Starting Date: March 2021
Estimated Completion Date: December 2022
Out for RFP to hire a General Contractor
Preconstruction meeting held May 26, 2022
Mobilization scheduled to start June 10, 2022
Framing at nurses' office in progress
MEP rough–in at nurses’ area in progress
Foundation at administration
completed
Structural steel work in progress
Estimated Budget
$2,236,000
Funding Source
Bond
ORGAN MOUNTAIN HS INTERCOM AND LIGHTING UPGRADES
ORGAN MOUNTAIN HS INTERCOM AND LIGHTING UPGRADES
ORGAN MOUNTAIN HS INTERCOM AND LIGHTING UPGRADES
Nine Degrees Architecture & Design Inc./ Fulcrum Contracting
This project will consist of installing a new intercom system as well as upgrading lighting with LED’s
Starting Date: February 2020
Estimated Completion Date: Sept. 2022
Construction: 70%
Estimated Budget
$514,292
Funding Source
Bond/PSCOC
VALLEY VIEW ELEMENTARY SCHOOL RE-ROOF
VALLEY VIEW ELEMENTARY SCHOOL RE-ROOF
ASA Architects
This project will consist of doing a complete tear-off of the existing roof and replacing it with a new one
Starting Date: March 2021
Design complete
Pending invitation to bid to solicit contractor
Estimated Completion Date: September 2022
Pending GC selection
Estimated Budget
$1,634,592
Funding Source
Bond/ PSCOC
2022 Bond Projects
(To Be Approved)
COLUMBIA ELEMENTARY SCHOOL
COLUMBIA ELEMENTARY SCHOOL
G. Sandoval Construction
This project will consist of demolishing existing facility & building a new school at the same site for 752 students
Purchasing working on Architect’s contract to design the new school
Estimated start date March 2022
Estimated completion of design March 2023
Working with general contractor to obtain permit to start demolition
Estimated start date March 2022
Estimated completion August 2022
Architect awarded contract May 23, 2022, to design the new school
Kick off meeting held May 25, 2022
Demolition is 30% complete
Construction of new school estimated to start May 2023
Construction of new school estimated to be complete August 2024
Estimated design and Demo. Budget
$7,127,115
Funding Source
Bond/PSCOC
LCPS OPERATIONS FACILITY
LCPS OPERATIONS FACILITY
Vigil & Associates
This project will consist of building multiple facilities at the 15-acre lot on Tashiro RD to accommodate Physical Plant, Materials Management, Construction and Food Service’s needs
Starting Date: March 2021
Estimated Completion Date: September 2023
Design complete
Waiting on Purchasing Dept. for advertisement and bid dates for construction
Estimated Budget
$22,250,000
Funding Source
Bond
Current LCPS Capital Outlay Projects
(In Progress)
FAIRACRES ES SITE DRAINAGE
FAIRACRES ES PARKING LOT IMPROVEMENTS
FAIRACRES ES SITE DRAINAGE & PARKING LOT IMPROVEMENTS
Vigil & Associates Architectural Group/ Renegade Construction
This project will consist of improving the site drainage on the north parking lot
Starting Date: February 2020
Estimated Completion Date: March 2022
Construction: 80%
Estimated Budget
$491,429.00
Funding Source
HB-33/PSCOC
HEALTH SERVICES OFFICE & ADDITIONS AT OLD BOOTS N BOURBON
HEALTH SERVICES OFFICE & ADDITIONS AT OLD BOOTS N BOURBON
HEALTH SERVICES OFFICE & ADDITIONS AT OLD BOOTS N BOURBON
ESA Construction
This project will consist of securing the main entrance with a secure vestibule
In Construction
Estimated Completion Date: July 2022
Construction: 70%
Estimated Budget
$247,140
Funding Source
HB-33
MESILLA ES SECURE VESTIBULE & FENCING
MESILLA ES SECURE VESTIBULE & FENCING
MESILLA ES SECURE VESTIBULE & FENCING
G. Sandoval Construction
This project will consist of securing the front office as well as securing the front playground area
In Construction
Estimated Completion Date: July 2022
Construction: 75%
Estimated Budget
$91,370
Funding Source
HB-33/PSCOC
OMHS HVAC UPGRADE
OMHS HVAC UPGRADE
ASA Architects
This project will consist of upgrading HVAC at the locker rooms.
Working on DP agreement
Estimated Budget
279,724
Funding Source
CRRSA/PSCOC
RIO GRANDE PREPARATORY INSTITUTE RE-ROOF
RIO GRANDE PREPARATORY INSTITUTE RE-ROOF
Desert Peak Architects/ Roof & Metal Company
This project will consist of doing a complete tear-off of the existing roof and replacing it with TPO
In Construction
Estimated Completion Date: December 2022
Construction: 30%
Estimated Budget
$1,085,986
Funding Source
HB-33/PSCOC
Future LCPS Capital Outlay Projects
(Coming Soon)
Projects with Matching Funding Sources
2018 Bond Projects
On February 6, 2018 the Las Cruces Public Schools Community Approved a 50 Million dollar general obligation package for the to support the capital outlay efforts for the Las Cruces Public Schools.
2018 Bond Projects
2022 Bond Projects
On November 2, 2021 the Las Cruces Public School Community Approved a $50 Million dollars general obligation bond package to support the capital outlay efforts of the Las Cruces Public Schools
2022 Bond Projects
Current LCPS Capital Projects
These are the current Capital Projects that the Operations Division is working on throughout the District
LCPS Future Capital Outlay Projects
Listed are the projects that we are currently proposing and working to create a plan and secure funding
Furniture, Painting, and Equipment
LCPS School Furniture Replacement Schedule
**This is an estimated schedule based on estimated available funding and is subject to change
School | Scheduled Furniture Replacement |
Sierra Middle School | 2022 |
Tombaugh Elementary School | 2022 |
Mesilla Elementary School | 2023 |
Organ Mountain High School--Phase 1 | 2023 |
Organ Mountain High School--Phase 2 | 2024 |
Sunrise Elementary School | 2024 |
Highland Elementary School | 2025 |
Conlee Elementary School | 2025 |
Desert Hills Elementary School | 2026 |
Cesar Chavez Elementary School | 2026 |
LCPS Equipment Replacement
**Equipment that is planned or currently being replaced and location
LCPS Physical Plant Painting Schedule
**This is an estimated plan to paint interior and exterior of our LCPS Facilities
Year | School | Interior | Exterior |