Weekend Traffic Advisory

Friday April 26, 2024, to Sunday April 28, 2024

This traffic alert details the locations of road construction and other events that will affect the flow of traffic this weekend. This information is subject to change. Check the Weekly Traffic Advisory Check the Special Traffic Advisory

Other state and local agencies are responsible for street construction work in New York City. Visit the Department of Design and Construction, the New York State Department of Transportation, the Port Authority of New York and New Jersey and MTA for more construction and traffic information. Check who operates bridges and tunnels

The times listed for closures for street fairs are for the actual times of the street fairs themselves. The streets may be closed for longer to allow for set-up and breakdown. Street fair organizers are generally permitted to begin set-up at 8 am and breakdown must be completed by 7 pm.

Manhattan

East 7 Street between Avenue A and 1st Avenue

This street will be closed from 9 am to 3 pm Monday to Friday through 5/10/24 to place boom lift on side for facade inspection.

West 16 Street between 9th Avenue and 10th Avenue

This street will be closed from 5 am to 3 pm Saturday and Sunday through 5/5/24 to facilitate crane operation.

East 17th Street between Park Avenue South and Irving Place

This street will be closed from 4 am Saturday to 10 pm Sunday through 5/5/24 to facilitate crane operation.

West 24th Street between 5th Avenue and 6th Avenue

This street will be closed from 5 am to 1 pm Saturday and Sunday through 4/28/24 for boom lift facade inspection.

East 26th Street between Park Avenue South and Lexington Avenue

This street will be closed from 7 am to 1 pm Saturday and Sunday through 5/12/24 for building inspection from boom truck.

West 27th Street between 12th Avenue and 11th Avenue

This street will be closed from 9 am to 3 pm Monday to Friday through 5/9/24 to facilitate crane operation.

West 38th Street between 6th Avenue and 5th Avenue

This street will be closed from 5 am to 1 pm Saturday and Sunday through 4/28/24 for building inspection from boom truck.

West 38th Street between 9th Avenue and 10th Avenue

This street will be closed This street will be closed from 6 am to 2 pm Saturday and Sunday through 5/26/24 to facilitate crane operation.

East 45th Street 5th Avenue and Madison Avenue

This street will be closed from 1 am to 10 am Saturday and Sunday through 4/28/24 to facilitate crane operation.

East 47th Street between Vanderbilt Avenue and Madison Avenue

This street will be closed 24/7 through 11/14/24 for Grand Central Terminal train shed project.

East 47th Street between Park Avenue and Vanderbilt Avenue

This street will be closed 24/7 through 11/14/24 for Grand Central Terminal train shed project.

West 47th Street between 8th Avenue and Broadway

This street will be closed from 12:01 am to 6 am Friday through 4/26/24 for use of knuckle boom for sign work.

East 48th Street between Madison Avenue and Park Avenue

This street will be closed 24/7 through 11/14/24 for Grand Central Terminal train shed project.

East 50th Street between 2nd Avenue and 1st Avenue

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 4/28/24 to repair sewer.

West 52nd Street between 8th Avenue and Broadway

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/5/24 to facilitate crane operation.

East 53rd Street between 5th Avenue and Madison Avenue

This street will be closed from 12:01 am Saturday to 9 pm Sunday through 4/28/24 to facilitate crane operation.

West 56 Street between 6th Avenue and 5th Avenue

This street will be closed from 10 pm to 6 am nightly through 4/30/34 to facilitate crane operation.

East 58th Street between Park Avenue and Lexington Avenue

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 4/28/24 to facilitate crane operation.

East 62nd Street between Madison Avenue and Park Avenue

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 4/28/24 for steam pad concrete curing.

West 64th Street between West End Avenue and Amsterdam Avenue

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/5/24 for gas main/service installation.

East 67th Street between 1st Avenue and 2nd Avenue

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/5/24 for building inspection from boom truck.

East 69th Street between Madison Avenue and Park Avenue

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/13/24 for steam pad concrete curing.

West 69th Street Broadway and Columbus Avenue

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/5/24 to facilitate crane operation.

East 70th Street between Lexington Avenue and 3rd Avenue

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/12/24 for major gas installation.

West 73rd Street between Columbus Avenue and Amsterdam Avenue

This street will be This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/10/24 for building inspection from boom truck.

East 74th Street between 1st Avenue and York Avenue

This street will be closed from 4 am to 10 pm Saturday and Sunday through 5/5/24 to main and assist mobile cranes to dismantle tower crane.

East 74th Street between York Avenue and Dead End

This street will be closed from 4 am to 10 pm Saturday and Sunday through 5/5/24 to dismantle tower crane.

West 74th Street between Columbus Avenue and Central Park West

This street will be This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/5/24 to facilitate crane operation.

East 77th Street between 2nd Avenue and 1st Avenue

This street will be closed from 9 am to 4 pm Friday through 5/17/24 for facade inspection and restoration.

East 77th Street between 2nd Avenue and 3rd Avenue

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/4/24 for sewer repair.

East 88th Street between 5th Avenue and Madison Avenue

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 4/28/24 to facilitate crane operation.

East 89th Street between Park Avenue and Madison Avenue

This street will be closed will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 4/27/24 building inspection from boom truck.

East 91st Street between 1st Avenue and York Avenue

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 7/9/24 to facilitate crane operation.

East 91st Street between Lexington Avenue and 3rd Avenue

This street will be closed from 8 am to 4 pm Saturday through 5/1/24 for knuckle boom and concrete pump.

West 94th Street between Amsterdam Avenue and Columbus Avenue

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 6/30/24 for major gas installation.

West 95th Street between West End Avenue and Pomander Walk (Broadway)

This street will be closed from 9 am to 4 pm Friday through 4/30/24 to facilitate crane operation.

West 112th Street between Broadway and Riverside Drive

This street will be closed This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/4/24 to facilitate crane operation.

East 122nd Street between Park Avenue and Lexington Avenue

This street will be closed from 9 pm Friday to 5 am Monday through 5/1/24 to erect the gentries for the Park Avenue viaduct.

East 121st Street between Park Avenue and Madison Avenue

This street will be 9 pm Friday to 5 am Monday through 5/1/24 to erect the gantries for the Park Avenue viaduct.

West 140th Street between Amsterdam Avenue and Hamilton Place

This street will be closed from 9 am to 5 pm Monday to Friday through 5/7/24 to facilitate crane operation.

West 162nd Street between Saint Nicholas Avenue and Broadway

This street will be closed from 9 am to 4 pm Monday to Friday through 5/7/24 to facilitate crane operation.

West 212th Street between Broadway and 10th Avenue

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/5/24 to facilitate crane operation.

Broadway between West 24th Street and West 25th Street

This street will be closed from 5 am to 11:59 am Saturday and Sunday through 4/28/24 for facade inspection-boom lift.

Vesey Street between Church Street and Broadway

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/26/24 for test pits & exploratory utility work.

Pine Street between Nassau Street and Broadway

This street will be closed from 7 am to 4 pm Monday to Friday, 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/15/24 for reconstruction of Nassau Street.

Clinton Street between Rivington Street and Stanton Street

This street will be closed from 9 am to 4 pm Friday through 5/13/24 for concrete operations.

Baruch Drive between Delancey Street South and Delancey Street North

This street will be closed from 7 am to 4 pm Monday to Friday through 5/3/24 for east side coast resiliency.

Franklin Street between Broadway and Cortlandt Alley

This street will be closed from 10 am to 10 pm Saturday regrades, gas valves.

Spruce Street between Nassau Street and Park Row

This street will be closed from 7 pm to 6 am weeknights through 5/3/24 for roadway marking.

Spruce Street between William Street and Gold Street

This street will be closed from 7 pm to 6 am weeknights through 5/3/24 for roadway marking.

Beekman Street between William Street and Gold Street

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/5/24 to facilitate crane operation.

King Street between Hudson Street and Greenwich Street

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/5/24 to facilitate crane operation.

Charlton Street between Hudson Street and Varick Street

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/5/24 to facilitate crane operation.

Spring Street between Hudson Street and Varick Street

This street will be from 7 am to 4 pm Monday to Friday through 5/13/24 for roadway closure in order to run a camera through the combined sewer on Spring Street.

Crosby Street between Prince Street and Jersey Street

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/5/24 to facilitate crane operation.

Wooster Street between Spring Street and Prince Street

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 4/28/24 to facilitate crane operation.

King Street between Hudson Street and Greenwich Street

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/4/24 for concrete pour.

Nassau Street between Spruce Street and Beekman Street

This street will be closed from 7 pm to 6 am weeknights through 5/3/24 for roadway marking.

York Avenue between East 74th Street and East 73rd Street

This street will be closed from 4 am to 10 pm Saturday and Sunday through 5/5/24 for tower crane boom landing and disassembly.

York Avenue between East 75th Street and East 74th Street

This street will be closed from 4 am to 10 pm Saturday and Sunday through 5/5/24 for tower crane boom landing and disassembly.

Delancey Street between Mangin Street and FDR Drive

This street will be closed from 7 am to 4 pm Monday to Friday through 5/1/24 for east side coast resiliency.

Battery Park Underpass (BPU) between Route 9A/West Street and FDR Drive

One tube at a time in either direction will be closed intermittently, Monday to Friday from 11 pm to 5 am next morning, through June 28, 2024, to facilitate inspection, maintenance, and repairs.

Morton Street between Hudson Street and Bedford Street

This street will be closed from 9 am to 4 pm Friday through 4/26/24 for lifting units to the roof top.

MacDougal Street between Minetta Lane and West 3rd Street

This street will be closed from 7 am to 3 pm Monday to Friday through 6/7/24 for major gas installation.

MacDougal Street between MacDougal Alley and West 8th Street

This street will be closed from 7 am to 4 pm Friday through 5/10/24 for concrete operations for foundation and super structure.

MacDougal Street between Bleecker Street and Minetta Lane

This street will be closed from 7 am to 3 pm Monday to Friday through 6/7/24 for major gas installation.

MacDougal Street between Washington Square North and MacDougal Alley

This street will be closed from 7 am to 4 pm Friday through 5/10/24 for concrete operations for foundation and super structure.

Ann Street between Park Row and Theater Alley

This street will be closed from 9 am to 4 pm Friday through 5/13/24 for pump concrete and to hoist materials.

Bleecker Street between Grove Street and Christopher Street

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 4/28/24 to facilitate crane operation.

Platt Street between Gold Street and Pearl Street

This street will be closed from 7 am to 4 pm Friday through 4/27/24 for concrete pouring.

Gouverneur Slip East between Water Street and South Street

This street will be closed from 7 am to 4 pm Friday, and 8 am to 4 pm Saturday through 5/6/24 for East side coast resiliency.

Jackson Street between Water Street and South Street

This street will be closed from 9 am to 4 pm Friday through 5/2/24 for east side coast resiliency.

Bethune Street between West Street and Washington Street

This street will be closed from 9 am to 4 pm Friday through 6/24/24 for major gas installation.

West Street between Jane Street and Horatio Street

This street will be closed from 7 am to 4 pm Monday to Friday through 4/29/24 for associated closure.

Horatio Street between West Street and Washington Street

This street will be closed from 7 am to 4 pm Monday to Friday through 4/29/24 to facilitate crane operation.

Jane Street between West Street and Washington Street

This street will be closed from 9 am to 4 pm Monday to Friday through 5/6/24 to facilitate crane operation.

Jane Street between Washington Street and Joe DiMaggio Highway

This street will be closed from 9 am to 4 pm Friday through 4/26/24 to excavate and install conduit for system reinforcement.

Washington Square East between Washington Place and Washington Square South

This street will be closed from 7 am to 4 pm Friday through 5/25/24 for special operations to include knuckle boom equipment.

Thompson Street between West 3rd Street and Bleecker Street

This street will be closed from 9 am to 4 pm Friday through 5/8/24 for booming operations.

Riverside Drive (Northbound Service Road) between West 152nd Street and West 153rd Street

This street will be closed 24/7 through 5/6/24 for safety reasons-NYCDOT contract HBM1165 rehab.

Harlem River Ramp (Northbound Entrance East 126th Street) between 2nd Avenue Southbound and 2nd Avenue Northbound

This street will be closed from 7 am to 6 pm Monday to Sunday through 5/10/24 for installation of new 13Kv feeders across Harlem River.

FDR Drive Southbound between Jackson Street and Cherry Street

Single-lane will be closed Friday from 11 pm to 7 am next morning, and Sunday from 11 pm to 10 am next morning. Double-lane will be closed Tuesday to Friday from 1 am to 5 am, Saturday from 1 am to 6 am, and Sunday from 1 am to 7 am. These closures are necessary to facilitate East Side Coastal Resiliency Project and will continue through September 11, 2026.

FDR Drive between Montgomery Street and East 15 Street

Single-lane northbound and/or southbound will be closed Monday to Thursday from 10 pm to 5 am next morning, Saturday from 12:01 am to 9 am, and Sunday from 1 am to 11 am. Double-lane will be closed Tuesday to Friday from 1 am to 5 am, Saturday from 1 am to 7 am, and Sunday from 1 am to 7 am. These closures are necessary to facilitate median reconstruction and will continue through August 15, 2026.

FDR Drive between East 73 Street and East 71 Street

Single-lane northbound will be closed Monday to Thursday from 10 pm to 5:30 am next morning, Friday from 11 pm to 10 am next morning, and Saturday from 11 pm to 11 am next morning. Double-lane northbound will be closed Tuesday to Friday from 1 am to 5 am, Saturday from 2 am to 6 am, and Sunday from 2 am to 7 am. Southbound FDR Drive service road between East 73 and East 71 Streets, FDR Exit Ramp (Exit 13), and Entrance Ramp to southbound FDR Drive will be closed Monday to Friday from 9:30 pm to 5 am next morning, Friday from 11 pm to 10 am next morning, and Saturday from 11 pm to 11 am next morning. These closures will continue through April 30, 2024, and are necessary to facilitate construction of Kellen Tower over the FDR Drive.

FDR Drive Southbound Exit 13 at East 73 Street

Southbound exit ramp at East 73 Street (Exit 13) will be closed Monday to Thursday from 11 pm to 5 am next morning, Friday from 11 pm to 10 am next morning, and Saturday from 11 pm to 11 am next morning, through May 17, 2024, to facilitate re-installing cathodic protection on the live oil line.

FDR Drive Southbound Entrance Ramp between East Houston Street and Delancey Street

Entrance ramp to southbound FDR will be closed Tuesday to Friday from 1 am to 5 am, Saturday from 2 am to 6 am, and Sunday from 2 am to 7 am, through June 30, 2024, to facilitate access to the manhole/underground facilities.

FDR Drive Southbound at 74 Street

Single-lane will be closed Monday to Thursday from 11 pm to 5:30 am next morning, Friday from 11 pm to 6:30 am next morning, and Sunday from 12 am to 11 am, through June 30, 2024, to facilitate facade repairs.

FDR Drive Southbound between East 112 Street and East 12 Street

Single-lane will be closed Monday to Thursday from 11 pm to 5:30 am next morning, Saturday from 12:01 am to 6:30 am, and Sunday from 1 am to 11 am. Double-lane will be closed Tuesday to Friday from 1 am to 5 am, Saturday from 2 am to 6 am, and Sunday from 2 am to 7 am. These closures are necessary to facilitate repairs to the underground facilities and will continue through May 31, 2024.

First Avenue Underpass between 40 Street and 49 Street

One tube at a time in either direction will be closed, Monday to Friday from 11 pm to 5 am next morning, through May 31, 2024, to facilitate inspection, maintenance, and repairs.

New Pedestrian Bridge and Fender Rehabilitation at Robert F. Kennedy Bridge

Single-lane in both directions of FDR Drive/Harlem River Drive will be closed and Willis Avenue ramp from the FDR Drive/Harlem River Drive northbound will be partially closed, Monday to Friday from 10:30 pm to 5 am, Saturday from 12 am to 6:30 am, and Sunday from 12 am to 11 am, through May 1, 2024.

Northbound Route 9A /West Street between Chambers Street and North Moore Street

One of four northbound lanes will be closed on Saturdays from 9 am to 6 pm on April 27, and May 11 to facilitate equipment delivery and installation at Borough of Manhattan Community College.

Northbound Route 9A/West Street between Warren Street and Hubert Street

Single-lane will be closed Monday to Friday from 10 pm to 5 am next morning, and Saturday and Sunday from 9 am to 6 pm. Double-lane will be closed Monday to Friday from 10 pm to 5 am next morning, Saturday from 1 am to 8 am, and Sunday from 2 am to 10 am. Triple-lane will be closed Monday to Friday from 1 am to 5 am, Saturday from 1 am to 7 am, and Sunday from 2 am to 8 am. These closures are necessary to facilitate Coastal Resiliency Project and will continue through July 1, 2024.

Southbound Route 9A/West Street between Hubert Street and Warren Street

Single-lane will be closed Monday to Friday from 9 pm to 5 am next morning, and Saturday and Sunday from 9 am to 6 pm. Double-lane will be closed Monday to Friday from 12:01 am to 5 am, Saturday from 1 am to 9 am, and Sunday from 2 am to 10 am. These closures are necessary to facilitate Coastal Resiliency Project and will continue through July 1, 2024.


Festivals, Parades and Events


Sikh Day Parade 2024 & Festival

The following streets will be closed for the Sikh Day Parade 2024 & Festival on Saturday, April 27th, 2024 at the discretion of the NYPD in Manhattan.

Location(s):
Formation:
  • 36th Street between Madison Avenue and 5th Avenue
  • 37th -38th Street between 5th Avenue and Park Avenue
Route:
  • Madison Avenue between 38th Street and 27th Street
Dispersal:
  • 27th Street between 5th Avenue and Park Avenue South
Festival:
  • Madison Avenue between 24th Street and 26th Street
  • 26th Street between Madison Avenue and Park Avenue

9/11 Memorial 5K Run/Walk

The following streets will be closed for the 9/11 Memorial 5K Run/Walks on Sunday, April 28th, 2024 at the discretion of the NYPD in Manhattan.

Location(s):
Formation:
  • Inside Battery Park / River Terrace between North End Avenue and Chambers Street
Route:
  • North End Avenue between Vesey Street and River Terrace
  • Chambers Street between River Terrace and West Street
  • Greenwich Street between Battery Place and Morris Street
  • Trinity Place between Morris Street and Edgar Street
  • Edgar Street between Trinity Place and Greenwich Street
  • Greenwich Street between Edgar Street and Cortlandt Way
  • Battery Place between 2nd Place and Little West Street
Dispersal:
  • Greenwich Street between Cortlandt Way and Fulton Street

Manhattan/Queens

Ed Koch/Queensboro Bridge

Single-lane Queens-bound south upper roadway will be closed 24/7, and double-lane will be closed Monday from 9:30 am to 1 pm, Tuesday to Friday from 9:30 am to 3 pm, Monday to Friday from 8 pm to 5 am next morning, and Saturday from 5 am to 2 pm. During second lane closure, one Manhattan-bound upper roadway lane will reverse to service Queens-bound traffic. Queens-bound south outer roadway will be closed Sunday to Saturday from 1 am to 6 am. These closures are necessary to facilitate replacement of upper roadway.


Manhattan/Brooklyn

Manhattan Bridge

Single-lane at a time will be closed on upper and lower roadways Tuesday from 9 pm to 3 am next morning to facilitate maintenance. At least one lane of traffic in each direction will be maintained at all times.

Brooklyn Bridge

Pearl Street entrance ramp to eastbound (Brooklyn-bound) Brooklyn Bridge (Ramp B) will be closed Monday to Friday from 11 pm to 5 am next morning to facilitate bridge rehabilitation.

Williamsburg Bridge

Single-lane Brooklyn-bound south outer roadway will be closed from Saturday 5 am to Monday 5 am, and Monday to Friday from 5 am to 7 pm. Single-lane Brooklyn-bound south inner roadway will be closed Monday from 10 am to 1 pm and Tuesday to Friday from 10 am to 3 pm. Single-lane Manhattan-bound outer roadway will be closed Monday to Friday from 7 pm to 5 am and single-lane Manhattan-bound inner roadway will be closed Monday to Friday from 8 pm to 5 am. These closures are necessary to facilitate Structural Strengthening and rehabilitation.


Manhattan/Bronx

Madison Avenue Bridge over Harlem River

Single-lane at a time in either direction will be closed Monday to Friday from 10 am to 2 pm. Single-lane in both directions will be closed Monday to Friday from 10 pm to 6 am next morning, and Saturday from 10 pm to 7 am next morning. Bridge will be fully closed Monday to Friday from 12:01 am to 5 am. Bronx-bound will be closed Saturday from 12:01 am to 6 am and Manhattan-bound will be closed Saturday from 12:01 am to 7 am. These closures are necessary to facilitate bridge rehabilitation and will continue through April 30, 2024.

Broadway Bridge over the Harlem River

Right lane in both directions will close Monday to Friday from 7 am to 3 pm and alternating center lane in either direction will close Monday to Friday from 10 am to 2 pm through April 26, 2024, to facilitate rope cable cleaning, machinery repairs, and electrical conduit installation. Alternating sidewalk closures will be in effect.

Washington Bridge over the Harlem River (181 Street)

Single-lane Manhattan-bound will be closed Monday to Friday from 12:01 am to 5 am through May 24, 2024, to facilitate installation of concrete barrier for the protected bike lane.


Bronx

East 142nd Street between Concord Avenue and Wales Avenue

This street will be closed from 7 am to 6 pm Monday to Friday for street paving.

East 153rd Street between Bergen Avenue and 3rd Avenue

This street will be closed from 9 am to 4 pm Friday through 5/10/24 for concrete pours and material deliveries.

West 169th Street between Nelson Avenue and Shakespeare Avenue

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 5/4/24 to facilitate crane operation.

East 176th Street between Belmont Avenue and Crotona Avenue

This street will be closed from 7 am to 4 pm Monday to Friday through 5/22/24 to facilitate crane operation.

East 177th Street between Grand Concourse and Morris Avenue

This street will be closed from 9 am to 3 pm Monday to Friday through 5/2/24 for new building construction.

East 180th Street between Ryer Avenue and Anthony Avenue

This street will be closed from 9 am to 2 pm Friday, and 8 am to 4 pm Saturday through 5/18/24 for concrete pouring and booming operations.

East 196th Street between Briggs Avenue and Bainbridge Avenue

This street will be closed from 4 pm to 11:59 pm Monday to Friday through 7/24/24 for tele handler for facade and roof work.

East 228th Street between Lowerre Place and White Plains Road

This street will be closed from 6 am to 4 pm Monday to Friday through 5/10/24 for mainline track repairs.

East 229th Street between Lowerre Place and White Plains Road

This street will be closed from 6 am to 4 pm Monday to Friday through 5/10/24 for mainline track repairs.

East 230th Street between Lowerre Place and White Plains Road

This street will be closed from 6 am to 4 pm Monday to Friday through 5/10/24 for mainline track repairs.

East 231st Street between Carpenter Avenue and White Plains Road

This street will be closed from 6 am to 4 pm Monday to Friday through 5/10/24 for mainline track repairs.

West 262nd Street between Huxley Avenue and Broadway

This street will be closed from 8 am to 5 pm Monday to Friday through 6/30/24 for use of concrete pumps, boom trucks and knuckle boom.

Continental Avenue between East 194th Street and Westchester Avenue/NYCTA Subway

This street will be closed from 8 am to 6 pm Saturday, and 9 am to 6 pm Sunday through 4/30/24 to hoist and erect precast plank, precast stairs, structural steel and materials.

Gerard Avenue between East 150th Street and East 151st Street

This street will be closed from 9 am to 2 pm Monday to Friday, and 8 am to 4 pm Saturday through 5/15/24 for new building construction.

Bush Street between Creston Avenue and Grand Concourse

This street will be closed from 8 am to 4 pm Monday to Friday through 5/17/24 to facilitate crane operation.

Creston Avenue between 196th Street and East Kingsbridge Road

This street will be closed from 9 am to 4 pm Friday through 7/24/24 to facilitate crane operation.

Weiher Court between Washington Avenue and 3rd Avenue

This street will be closed from 8 am to 4 pm Monday to Friday through 5/31/24 for use of crane to erect new building.

Washington Avenue between Claremont Parkway and East 172nd Street

This street will be closed from 9 am to 4 pm through 4/29/24 to facilitate crane operation.

Park Avenue between East 122nd Street and intersection

This street will be closed 9 pm Friday to 5 am Monday through 5/1/24 to erect the gantries for the Park Avenue viaduct.

Park Avenue between East 138th Street and East 135th Street

This street will be closed from 7 am to 6 pm Monday to Friday through 4/30/24 for all superstructure operations.

Andrews Avenue between West 176th Street and West Tremont Avenue

This street will be closed from 9 am to 2 pm Monday to Friday and/or Saturday from 8 am to 4 pm through 4/30/24 for hoisting and pumping operations.

Andrews Avenue between Hall of Fame Terrace and West 183 Street

This street will be closed from 6 pm to 2 am Monday to Friday through 6/29/24 for boom truck for lifting materials to school building.

Whitlock Avenue between Aldus Street and East 165th Street

This street will be closed from 9 am to 5 pm Monday to Friday, and 8 am to 6 pm Saturday through 5/4/24 to facilitate crane operation.

Cruger Avenue between Sagamore Street and Bronxdale Avenue

This street will be closed from 8 am to 5 pm Friday through 6/28/24 for MTA contract C-35311 work zone and MP 6.

Cruger Avenue between Adee Avenue and Burke Avenue

This street will be closed from 9 am to 3 pm Monday to Friday to facilitate crane operation.

Villa Avenue between East 205th Street and Van Cortlandt Avenue East

This street will be closed from 8 am to 5 pm Monday to Friday through 5/12/24 for boom and knuckle boom to work on building.

Shore Road Bridge over the Hutchinson River

Single-lane northbound will be closed Monday to Friday from 7 am to 9 am and single-lane in both directions will be closed from 9 am to 1 pm and 10 pm to 7 am next morning through May 10, 2024 to facilitate maintenance. One lane of traffic in each direction will be maintained at all times.

Anthony Avenue between East 176th Street and East 175th Street

This street will be closed from 9 am to 4 pm Friday through 5/10/24 to facilitate crane operation.

Secor Avenue between Conner Street and Boston Road

This street will be closed from 10 pm Friday to 5 am Monday through 4/29/24 for mainline track repairs.

Dyre Avenue between Conner Street and Light Street

This street will be closed from 10 pm Friday to 5 am Monday through 4/29/24 for mainline track repairs.

Westchester Avenue Bridge between Water Place and Middletown Road

This street will be closed from 10 pm to 5 am weeknights through 4/30/24 for NYCDOT HBX1086 rehab of Westchester Avenue Bridge over Hutchinson River Parkway.

Westchester Avenue Bridge between Water Place and Ericson Place

Single-lane in each direction will be closed Monday to Friday from 9 pm to 6 am next morning to facilitate milling and paving on the bridge. At least one travel lane in each direction will remain open at all times. These closures will continue through April 26, 2024.

Henry Hudson Parkway Bridge over Broadway

Northbound Broadway, in the vicinity of the bridge overpass, will be reduced to one travel lane and parking lane will be closed, through April 30, 2024, to facilitate bridge rehabilitation.

Hutchinson River Parkway Bridge

Double-lane in either direction will be closed Monday to Friday from 12:01 am to 5:30 am through April 26, 2024, to facilitate bridge maintenance.

Hutchinson River Parkway Northbound between Exit 1B (East Tremont/Westchester Avenues) and Entrance ramp from Hutchinson River Parkway East

Single-lane northbound will close Monday to Thursday from 9 am to 3 pm and 10 pm to 5 am next morning, Friday from 10 am to 3 pm and 11 pm to 3 pm next day, and Saturday from 11 pm to 2 pm next day. Double-lane northbound will close Monday to Friday from 12:01 am to 5 am, Saturday from 1 am to 7 am, and Sunday from 2 am to 9 am. These closures are necessary to facilitate Westchester Avenue Bridge reconstruction and will continue through June 30, 2024.

Hutchinson River Parkway Southbound between Exit 1C (Pelham Parkway) and Entrance ramp from Westchester Avenue

Single-lane southbound will close Monday to Thursday from 10 am to 3 pm and 10 pm to 5 am next morning, Friday from 10 am to 3 pm and 10 pm to 6 am next morning, and Saturday from 10 pm to 2 pm next day. Double-lane southbound will close Monday to Friday from 12:01 am to 5 am, Saturday from 1 am to 6:30 am, and Sunday from 2 am to 9 am. These closures are necessary to facilitate Westchester Avenue Bridge reconstruction and will continue through June 30, 2024.

Hutchinson River Parkway in the vicinity of the Westchester Avenue Bridge

Single-lane in both directions will be closed Monday to Friday from 10 pm to 5 am and double-lane will be closed from 12:01 am to 4 am, through April 26, 2024, to facilitate roadway light installation as part of the Westchester Avenue Bridge rehabilitation.

Entrance Ramp from Southbound Sheridan Boulevard (NY-895) to Westbound Bruckner Expressway (I-278)

This ramp will be closed through December 24, 2024, to facilitate Hunts Point Interstate Access Improvement Project. Trucks and buses are advised to use the exit ramp towards Edgewater Road/Hunts Point Market and follow the detour signs and use the Leggett Avenue entrance ramp to westbound Bruckner Expressway. Cars are advised to use the temporary exit ramp towards Whitlock Avenue and follow the detour signs to westbound Bruckner Expressway.

Grand Concourse Bridge over Metro North Railroad Hudson Line between 151 Street and 153 Street

Two lanes of traffic in both directions are shifted to the southbound lanes and structural steel repair work will continue through April 26, 2024, Monday to Friday from 7 am to 3:30 pm and 9 pm to 5 am next morning.

Major Deegan Expressway (northbound) between Exit 3 and Entrance ramp north of East 138 Street

Right-lane will become an exit only lane at Exit 3 24/7. Additional lane will be closed Monday to Friday from 11 pm to 5 am, Saturday and Sunday from 1 am to 8 am, and Sunday night from 10 pm to 5 am next morning through March 3, 2025 to facilitate East 138 Street Bridge replacement. Full closure may occur Monday to Friday between 12 am and 5 am for demolition and erection of the superstructure.

Major Deegan Expressway (southbound) between Exit 3 and Entrance ramp south of East 138 Street

Right-lane will become an exit only lane at Exit 3 24/7. Additional lane will be closed Monday to Friday from 11 pm to 5 am, Saturday and Sunday from 1 am to 8 am, and Sunday night from 10 pm to 5 am next morning through March 3, 2025 to facilitate East 138 Street Bridge replacement. Southbound exit ramp to 138 Street bridge will be closed Monday to Friday from 11 pm to 5 am, Friday from 11 pm to 6 am next morning, Saturday from 11 pm to 9 am next morning, and Sunday from 11 pm to 5 am next morning to facilitate water main connections.


Brooklyn/Queens

Metropolitan Avenue Bridge over English Kills

Single-lane in either direction will be closed Monday to Friday from 11 pm to 5 am next morning, through May 3, 2024, to facilitate bridge maintenance. At least one lane in each direction will be maintained at all times.


Brooklyn

Brooklyn-Queens Expressway between Atlantic Avenue and Clark Street

Single-lane Queens-bound and the Atlantic Avenue entrance ramp to Queens-bound Brooklyn-Queens Expressway will be closed Monday to Friday from 12 am to 5 am through May 10, 2024, to facilitate core extraction and testing.

Brooklyn-Queens Expressway between Atlantic Avenue and Sands Street

Queens-bound will be closed from Saturday 2 am to Monday 4 am, to facilitate critical repairs of the triple cantilever structure. Queens-bound Brooklyn-Queens Expressway entrance ramps at Atlantic Avenue, 3 Avenue, Prospect Expressway, and Hamilton Avenue, will also be closed. Motorists may use the Tillary Street entrance ramp to access Queens-bound mainline. On Atlantic Avenue between Clinton Street and Boerum Place, south side parking lane will accommodate right and thru traffic while two eastbound lanes will be dedicated to left-turn traffic onto Boerum Place. On Canal Street between Chrystie and Allen Streets, westbound lanes will be closed.

Brooklyn-Queens Expressway between Vine Street Entrance Ramp and Atlantic Avenue

Single-lane Staten Island-bound will be closed Monday to Friday from 1 am to 5 am, Saturday from 1 am to 6 am, and Sunday from 1 am to 9 am, through May 3, 2024, to facilitate core extraction and testing.

7 Avenue Bridge over LIRR between 64 Street and 62 Street

Approximately 35 parking spaces will be eliminated, and travel lanes will be shifted to the parking lanes, Monday to Friday from 7 am to 6 pm, through May 17, 2024, to facilitate rehabilitation.

18 Avenue Bridge over LIRR between 52 Street and 54 Street

Approximately 16 parking spaces will be eliminated, and travel lanes will be shifted to the parking lanes, Monday to Friday from 7 am to 6 pm, through May 17, 2024, to facilitate rehabilitation.

South 3rd Street between Bedford Avenue and Driggs Avenue

This street will be closed from 9 am to 4 pm Friday through 6/11/24 for booming and concrete operations.

South 9th Street between Berry Street and Bedford Avenue

This street will be closed from 9 am to 4 pm Friday through 6/4/24 for material booming and concrete pouring.

North 6th Street between Wythe Avenue and Berry Street

This street will be closed from 9 am to 4 pm Friday through 5/17/24 to facilitate crane operation.

North 6th Street between Berry Street and Bedford Avenue

This street will be closed from 9 am to 4 pm Friday through 5/17/24 for associated closure.

North 9th Street between Kent Avenue and Wythe Avenue

This street will be closed from 9 am to 4 pm Friday through 6/1/24 to facilitate crane operation.

East 9th Street between Kings Highway and Quentin Road

This street will be closed from 9 am to 4 pm Friday through 5/31/24 for use of concrete pump, knuckle boom for new building construction.

12th Street between 4th Avenue and 5th Avenue

This street will be closed from 9 am to 4 pm Friday through 5/30/24 for hoisting and pumping operations.

West 15th Street between Surf Avenue and Mermaid Avenue

This street will be closed from 9 am to 4 pm Friday through 5/31/24 for telescopic lift.

East 18th Street between Kings Highway and Quentin Road

This street will be closed from 9 am to 4 pm Friday through 6/1/24 for use of boom, knuckle boom and concrete pump to work on new building.

East 22nd Street between Beverly Road and Duryea Place

This street will be closed from 9 am to 4 pm Friday through 5/9/24 for concrete pump and knuckle boom use.

25th Street between 4th Avenue and 5th Avenue

This street will be closed from 9 am to 4 pm Friday through 5/8/24 to facilitate crane operation.

East 26th Street between Foster Avenue and Newkirk Avenue

This street will be closed from 9 am to 4 pm Friday through 5/7/24 for use of boom and knuckle boom to work on new building.

37 Street between 13 Avenue and Church Avenue

This street will be closed from 9 am to 4 pm Friday through 4/30/24 for material deliveries and concrete pours.

46 Street between 13 Avenue and 14 Avenue

This street will be closed from 9 am to 4 pm Friday through 4/30/24 for lifting material to rooftop.

East 49th Street between Rutland Road and Winthrop Street

This street will be closed 9 am to 4 pm Friday through 5/31/24 to inspect sewer and repair collapsed roadway.

54 Street between 16th Avenue and 17th Avenue

This street will be closed from 9 am to 3 pm Monday to Friday when school is in session 9 am to 4 pm Friday through 4/30/24 to facilitate crane operation.

62nd Street between 13 Avenue and 14 Avenue

This street will be closed from 9 am to 4 pm Friday through 5/25/24 for boom, knuckle boom and concrete pump to work on our new building.

Carroll Street between 6th Avenue and 7th Avenue

This street will be closed from 8 am to 5 pm Saturday through 5/4/24 to facilitate crane operation.

Carroll Street between Bond Street and Body of Water

This street will be closed from 9 am to 4 pm Friday through 6/30/24 for use of concrete pump and knuckle boom truck.

Chapel Street between Jay Street and Flatbush Avenue Exit

This street will be closed from 9 am to 4 pm Friday through 6/30/24 for use of concrete pump and knuckle boom truck.

Duryea Place between Flatbush Avenue and East 22nd Street

This street will be closed from 9 am to 4 pm Friday through 5/15/24 for concrete pump and knuckle boom use.

Boerum Street between White Street and Bogart Street

This street will be closed from 9 am to 4 pm

Bouck Court between Shell Road and West 3rd Street

This street will be closed from 10 pm Friday to 8 pm Sunday through 5/12/24 to facilitate crane operation.

Shell Road between Avenue Y and Bouck Court

This street will be closed from 10 pm Friday to 8 pm Sunday through 5/12/24 to facilitate crane operation.

Shell Road between Bouck Court and Avenue X

This street will be closed from 10 pm Friday to 8 pm Sunday through 5/12/24 to facilitate crane operation.

Battery Avenue between 86 Street and 88 Street

This street will be closed from 9 am to 4 pm Friday through 5/3/24 to lift on roadway for window caulking.

Webster Place between East 16 Street and Prospect Avenue

This street will be closed from 9 am to 4 pm Friday through 5/19/24 to build conduit to 5 Webster Place.

Douglass Street between 4th Avenue and 3rd Avenue

This street will be closed from 9 am to 4 pm Friday through 7/11/24 to facilitate crane operation.

Eckford Street between Driggs Avenue and Engert Avenue

This street will be closed from 9 am to 4 pm Friday through 5/6/24 for use of boom, knuckle boom and concrete pump to work on new building.

Lott Street between Tilden Avenue and Beverly Road

This street will be closed from 9 am to 4 pm Friday through 5/31/24 for concrete pump and knuckle boom.

Gallatin Place between Livingston Street and Fulton Street

This street will be closed from 9 am to 4 pm Friday through 7/27/24 for new building.

Hudson Avenue between Dekalb Avenue and Fulton Street

This street will be close from 9 am to 4 pm Friday through 5/29/24 for use of knuckle boom/concrete pump.

Lawrence Street between Fulton Street and Willoughby Street

This street will be closed from 9 am to 4 pm Friday through 7/27/24 for boom, knuckle boom and concrete pump to work on new building.

Sandford Street between Myrtle Avenue and Park Avenue

This street will be closed from 9 am to 4 pm Friday through 5/10/24 for new building construction, concrete pouring operations.

Ainslie Street between Manhattan Avenue and Leonard Street

This street will be closed from 9 am to 4 pm Friday through 4/28/24 for booming and concrete operations.

Linden Street between Wilson Avenue and Knickerbocker Avenue

This street will be closed from 7 am to 4 pm Monday to Friday through 5/24/24 to facilitate crane operation.

Debevoise Avenue between Maspeth Avenue and Jackson Street

This street will be closed from 9 am to 4 pm Friday through 6/5/24 to hoist and erect structural steel and building materials.

Garden Street between Flushing Avenue and Bushwick Avenue

This street will be closed from 9 am to 4 pm Friday through 4/30/24 for concrete pump and knuckle boom operations.

St. Felix Street between Dekalb Avenue and Fulton Avenue

This street will be closed from 9 am to 4 pm Weekdays through 5/6/24 for emergency front building facade work with boom lift.

Van Sinderen Avenue between Herkimer Street and Fulton Street

This street will be closed from 7 am to 6 pm Saturday through 6/17/24 for major service.

Vermont Street between Jamaica Avenue and Fulton Street

This street will be closed from 9 am to 4 pm Friday through 4/30/24 for use of boom truck and concrete boom.

New Jersey Avenue between Jamaica Avenue and Fulton Street

This street will be from 9 am to 4 pm Friday through 4/30/24 for use of boom truck and concrete boom.

Clinton Street between Pierrepont Street and Cadman Plaza West

This street will be closed from 9 am to 4 pm Friday through 7/16/24 to facilitate crane operation.

Church Avenue between 37 Street and Old New Utrecht Road

This street will be closed from 9 am to 4 pm Friday through 4/30/24 for material deliveries and concrete pours.

Sanford Street between Myrtle Avenue and Park Avenue

This street will be closed from 9 am to 4 pm Friday through 7/4/24 to facilitate crane operation.

Grand Avenue between Fulton Street and Lefferts Place

This street will be closed from 9 am to 4 pm Friday through 7/8/24 for gas main installation.

Grand Avenue between Fulton Street and Putnam Avenue

This street will be closed from 9 am to 4 pm Friday through 7/8/24 for gas main installation.

Grand Avenue between Pacific Street and Dean Street

This street will be closed from 9 am to 2 pm Monday to Friday through 5/28/24 for use of boom, knuckle boom and concrete pump to work on new building.

Dean Street between Franklin Avenue and Classon Avenue

This street will be closed from 9 am to 4 pm Friday through 6/7/24 for use of boom, knuckle boom and concrete pump to work on new building.

Eldert Street between Knickerbocker Avenue and Irving Avenue

This street will be closed from 9 am to 4 pm Friday through 5/31/24 for use of man lift to remove building facade.

Hart Street between Broadway and Stuyvesant Street

This street will be closed from 9 am to 4 pm Friday through 6/30/24 for concrete pump usage.

Herkimer Street between Havens Place and Van Sinderen Avenue

This street will be closed from 9 am to 4 pm Friday through 6/17/24 for major service to 2440 Fulton Street.

Herkimer Street between Havens Place and Intersection

This street will be closed from 9 am to 4 pm Friday through 6/17/24 for major service.

Herkimer Street between Havens Place and Jardine Place

This street will be closed from 9 am to 4 pm Friday through 6/17/24 for major service.

Havens Place between Herkimer Street and Atlantic Avenue

This street will be closed from 9 am to 4 pm Friday through 6/17/24 for major service.

India Street between Body of water (Dead End) and West Street

This street will be closed from 7 am to 6 pm Monday to Friday through 5/31/24 for large concrete pours.

Richardson Street between Lorimer Street and Union Avenue

This street will be closed from 9 am to 4 pm Friday through 7/8/24 to facilitate crane operation.

Prospect Place between Buffalo Avenue and Ralph Avenue

This street will be closed from 9 am to 4 pm Monday to Friday through 5/11/24 to facilitate crane operation.


Festivals, Parades and Events


NYC Runs Brooklyn

The following streets will be closed for the NYC Runs Brooklyn on Sunday, April 28th, 2024 at the discretion of the NYPD in Brooklyn.

Embargo:    Special Event Construction Embargo / April 19th, 2024 - April 28th, 2024

Location(s):
Formation:
  • Berry Street between North 12th Street and Nassau Avenue
  • Nassau Avenue between Berry Street and Lorimer Street/Bedford Avenue
  • Lorimer Street between Bedford Avenue and Driggs Avenue
  • Driggs Avenue between Lorimer Street and North 12th Street
  • North 12th Street between Driggs Avenue and Berry Street
  • Bedford Avenue between North 12th Street and Lorimer Street/Nassau Avenue
Route:
  • Nassau Avenue between Manhattan Avenue and Lorimer Street
  • Manhattan Avenue between Nassau Avenue and Greenpoint Avenue
  • Greenpoint Avenue between Manhattan Avenue and Franklin Street
  • Franklin Street between Greenpoint Avenue and Kent Avenue
  • Kent Avenue between Franklin Street and Williamsburg Street West
  • Williamsburg Street West between Kent Avenue and Flushing Avenue
  • Flushing Avenue between Williamsburg Street West and Navy Street
  • Navy Street between Flushing Avenue and York Street
  • York Street between Navy Street and Gold Street
  • Gold Street between York Street and Front Street
  • Front Street between Gold Street and Old Fulton Street
  • Old Fulton Street between Front Street and Cadman Plaza West
  • Cadman Plaza West between Old Fulton Street and Montague Street
  • Court Street between Montague Street and Joralemon Street
  • Joralemon Street between Court Street and Brooklyn Bridge Boulevard/Fulton Street
  • Fulton Street between Brooklyn Bridge Boulevard/Joralemon Street and Flatbush Avenue
  • Flatbush Avenue between Fulton Street and Grand Army Plaza
  • Grand Army Plaza between Flatbush Avenue and Eastern Parkway
  • Eastern Parkway between Grand Army Plaza and Brooklyn Avenue
  • Flatbush Avenue between Grand Army Plaza and Empire Boulevard

Queens

Cross Island Parkway in the vicinity of the Hillside Avenue Bridge

Single-lane at a time in either direction will be closed Monday to Friday from 10 am to 3 pm through April 30, 2024, to facilitate installation of shielding under the bridge. Due to clearance reduction, oversized emergency vehicles are advised to exit prior to the bridge overpass.

Francis Lewis Boulevard Bridge over Belt System Laurelton Parkway

Single-lane in both directions, on the bridge, will be closed Monday to Friday from 9 am to 4 pm through April 30, 2024, and west sidewalk will remain closed. Also, single-lane in both directions on the Belt System Lauralton Parkway underpass will be closed Monday to Friday from 10 pm to 5 am next morning and double-lane will be closed from 1 am to 5 am through May 22, 2024. One lane in each direction will be maintained. These closures are necessary to facilitate bridge underdeck rehabilitation.

Belt Parkway/Laurelton Parkway

Shoulder and adjacent lane in both directions will be closed Monday to Friday from 10 am to 3 pm, through November 1, 2024, to facilitate electrical repairs.

Belt Parkway between Exit 21B and Exit 20

Single-lane westbound will be closed Monday to Thursday from 10 am to 2 pm and 10 pm to 5 am next morning, Friday from 10 pm to 6 am next morning, and Saturday from 10 pm to 11 am next morning. Double-lane westbound will be closed Monday to Friday from 1 am to 5 am, Saturday from 1 am to 6 am, and Sunday from 2 am to 9 am. These closures are necessary to facilitate JFK Redevelopment Program and will continue through December 31, 2025.

Clearview Expressway between Throgs Neck Bridge and 500 feet south of Grand Central Parkway

Shoulder and adjacent lane in both directions will be closed Monday to Friday from 9 am to 3 pm, through November 1, 2024, to facilitate electrical repairs.

Cross Island Parkway (entire length)

Shoulder and adjacent lane in both directions will be closed Monday to Friday from 10 am to 3 pm, through November 1, 2024, to facilitate electrical repairs.

Grand Central Parkway between RFK Bridge and Nassau County Line

Shoulder and adjacent lane will be closed Monday to Friday from 10 am to 2 pm on the eastbound and from 10 am to 3 pm on the westbound, through November 1, 2024, to facilitate electrical repairs.

Grand Central Parkway between Long Island Expressway and 62 Drive Pedestrian Bridge over Grand Central Parkway

Single-lane in both directions will be closed Monday to Friday from 10 pm to 5 am next morning and double-lane will be closed from 12:01 am to 5 am. Lane reduction from 18 feet to 11 feet wide will occur Monday to Friday from 10 pm to 5 am next morning on the eastbound Collector Distributor Road ramp from eastbound Grand Central Parkway to eastbound Long Islang Expressway. Lane reduction from 15 feet to 10 feet wide will occur Monday to Friday from 12:01 am to 5 am on the ramp from eastbound Grand Central Parkway to eastbound Long Island Expressway. These closures are necessary to facilitate flood mitigations and will continue through June 30, 2024.

Grand Central Parkway between 47 Street and Hazen Street

Single-lane in both directions will be closed Monday to Friday from 10 pm to 5 am next morning through June 30, 2024 to facilitate flood mitigation.

Hillside Avenue Bridge over Cross Island Parkway

Single-lane westbound will be closed Monday to Friday from 9 am to 7 pm, Saturday from 8 am to 6 pm, and Sunday from 9 am to 6 pm. Double-lane westbound will be closed Monday to Friday from 10 am to 2 pm. North sidewalk will remain closed. These closures are necessary to facilitate bridge rehabilitation and will continue through April 30, 2024.

Van Wyck Expressway Viaduct Rehabilitation

Single-lane in both directions will be closed Monday to Thursday from 10 pm to 5 am next morning, Saturday and Sunday from 1 am to 6 am. Double-lane in both directions will be closed Monday to Friday from 1 am to 5 am, Saturday and Sunday from 2 am to 6 am. These closures are necessary to facilitate bridge rehabilitation and will continue through September 30, 2024.

Van Wyck Expressway

Single-lane in both directions will be closed Monday to Friday from 10 am to 2 pm, Monday to Thursday from 10 pm to 6 am, Friday from 11:59 pm to 8 am, Saturday from 11 pm to 10 am, and Sunday from 10 pm to 6 am. Double-lane in both directions will be closed Monday to Thursday from 11 pm to 4 am and Sunday from 1 am to 7 am. Double-lane will be closed Friday from 11 pm to 7 am for northbound and from 11 pm to 5 am for southbound. The exit and entrance ramps along the north and southbound of the expressway may also be closed. These closures are necessary to facilitate roadway widening and will continue through July 14, 2025.

Van Wyck Expressway between Northern Boulevard and Long Island Expressway

Double-lane in either direction will be closed Monday and Friday from 12:01 am to 5 am, Tuesday to Thursday from 11 pm to 5 am next morning, Saturday from 12:01 am to 6 am, and Sunday from 12:01 am to 9 am for southbound and 12:01 am to 7:30 am for northbound. These closures are necessary to facilitate reconstruction of Roosevelt Avenue Bridge and will continue through May 10, 2024.

Van Wyck Expressway between Long Island Expressway and Pedestrian Bridge over Van Wyck Expressway

Single-lane in both directions will be closed Monday to Friday from 11 pm to 5 am. Double-lane will be closed Monday to Friday from 12:01 am to 6 am for southbound and from 12:01 am to 5:30 am for northbound. These closures are necessary to facilitate flood mitigations and will continue through June 30, 2024.

Van Wyck Expressway in the vicinity of Roosevelt Avenue Bridge

Single-lane northbound will be closed Monday to Friday from 9:30 am to 2 pm, Monday to Thursday from 10 pm to 5 am next morning, Friday from 9 pm to Saturday 12 pm, and Saturday 8 pm to Sunday 12 pm. Single-lane southbound will be closed Monday to Friday from 9:30 am to 2 pm, Monday to Thursday from 10 pm to 5 am next morning, Friday from 9 pm to Saturday 3 pm, and Saturday 8 pm to Sunday 3 pm. Double-lane northbound will be closed Monday to Friday from 12:01 am to 5 am, Saturday from 12:01 am to 6 am, and Sunday from 12:01 am to 7:30 am. Double-lane southbound will be closed Monday to Friday from 12:01 am to 6 am, Saturday from 12:01 am to 6 am, and Sunday from 12:01 am to 9 am. At least one lane of traffic in each direction will be maintained at all times. These closures are necessary to facilitate reconstruction of Roosevelt Avenue Bridge and will continue through July 2, 2024.

Springfield Boulevard Bridge over Belt Southern Parkway

Single-lane in each direction on the Belt Parkway, in the vicinity of the Springfield Boulevard Bridge overpass, will be closed Monday to Friday from 10 pm to 5 am next morning and double-lane will be closed from1 am to 5 am. These closures are necessary to facilitate rehabilitation of the Springfield Boulevard Bridge and will continue through April 26, 2024. One lane in each direction will be maintained. Also, Single-lane in each direction on the bridge will be closed Monday to Friday from 9 am to 2 pm through April 30, 2024, to facilitate median reconstruction.

Laurelton Parkway in the vicinity of 130 Avenue Bridge

Single-lane in both directions will be closed Monday to Friday from 10 pm to 5 am and double-lane will be closed from 1 am to 5 am through April 30, 2024, to facilitate installation of Shielding Brackets on the under-deck of the 130 Street Bridge. One lane in each direction will be maintained. Due to clearance reduction, vehicle's height over 9-5 inches for northbound and 7-11 inches for southbound, are advised to exit prior to approaching the 130 Street Bridge overpass.

Long Island Expressway between Clearview Expressway and Springfield Boulevard

Single-lane eastbound mainline will be closed Monday to Friday from 10 am to 2 pm, Monday to Thursday from 11 pm to 5 am next morning, Friday from 11 pm to 7 am next morning, and Saturday from 11 pm to 11 am next morning. Double-lane eastbound mainline will be closed Monday to Friday from 1 am to 5 am, Saturday from 1 am to 7 am, and Sunday from 2 am to 9 am. Single-lane westbound mainline will be closed Monday to Friday from 10 am to 3 pm, Monday to Thursday from 11 pm to 5 am next morning, Friday from 10 pm to 6 am next morning, and Saturday from 10 pm to 11 am next morning. Double-lane westbound mainline will be closed Monday to Friday from 1 am to 5 am, Saturday from 1 am to 6 am, and Sunday from 2 am to 9 am. Mainline closures will continue through September 30, 2024. Single-lane of service road (Horace Harding Expressway) westbound will be closed Monday to Friday from 10 am to 3 pm, Monday to Thursday from 11 pm to 5 am next morning, Friday from 11 pm to Saturday 3 pm, and Saturday from 11 pm to 9 am next morning. Service road closures will continue through December 31, 2024. These closures are to facilitate replacement of Oceania Street Bridge.

Long Island Expressway between Van Wyck Expressway and Grand Central Parkway

Single-lane westbound on the mainline and service road will be closed Monday to Friday from 10 pm to 5 am next morning. Single-lane eastbound will be closed Monday to Friday from 11 pm to 6 am next morning. Ramp from eastbound service road to eastbound Grand Central Parkway will be closed Monday to Friday from 12:01 am to 5 am and motorists are advised to detour to next entrance ramp by 72 Road. These closures are necessary to facilitate flood mitigations and will continue through June 30, 2024.

Long Island Expressway between Queens Midtown Tunnel and Nassau County Line

Shoulder and adjacent lane will be closed Monday to Friday from 10 am to 2 pm on the eastbound and from 10 am to 3 pm on the westbound, through November 1, 2024, to facilitate electrical repairs.

Long Island Expressway between Queens Midtown Tunnel and Maurice Avenue

Single-lane eastbound will be closed Monday to Friday from 10 am to 2 pm and from 11 pm to 6 am next morning, Saturday from 12:01 am to 10 am, and Sunday from 12:01 am to 11 am and from 10 pm to 6 am next morning. Double-lane eastbound will be closed Monday to Friday from 1 am to 6 am, Saturday from 2 am to 8 am, and Sunday from 2 am to 8 am. Single-lane westbound will be closed Monday to Thursday from 10 am to 3 pm and from 10 pm to 5 am next morning, Friday from 10 am to 3 pm and from 10 pm to 7 am next morning, Saturday from 10 pm to 10 am next morning, and Sunday from 10 pm to 5 am next morning. Double-lane westbound will be closed Monday to Friday from 12:01 am to 5 am, Saturday from 12:01 am to 6 am, and Sunday from 12:01 am to 7 am. Intermittent 15-minute full closure in one direction at a time may occur Monday to Saturday between 2 am and 5 am except holidays and embargo days for maximum of five nights. On and Off-Ramps within this segment will be reduced to 14 feet Monday to Saturday from 10 pm to 5 am next morning. These closures are necessary to facilitate installation of ATDM and ITS equipment and will continue through September 27, 2024.

Long Island Expressway between Maurice Avenue and College Point Boulevard

Single-lane eastbound will be closed Monday to Friday from 10 am to 2 pm and from 11 pm to 6 am next morning, Saturday from 12:01 am to 7 am, and Sunday from 12:01 am to 9 am. Double-lane eastbound will be closed Monday to Friday from 1 am to 6 am, Saturday from 2 am to 7 am, and Sunday from 2 am to 7 am. Single-lane westbound will be closed Monday to Thursday from 10 am to 3 pm and from 10 pm to 5 am next morning, Friday from 10 am to 3 pm and from 10 pm to 6 am next morning, and Saturday from 11 pm to 6 am next morning. Double-lane westbound will be closed Monday to Friday from 1 am to 5 am, Saturday from 12:01 am to 6 am, and Sunday from 12:01 am to 6 am. Intermittent 15-minute full closure in one direction at a time may occur Monday to Saturday between 2 am and 5 am except holidays and embargo days for maximum of five nights. On and Off-Ramps within this segment will be reduced to 14 feet Monday to Saturday from 10 pm to 5 am next morning. These closures are necessary to facilitate installation of ATDM and ITS equipment and will continue through September 27, 2024.

Long Island Expressway between College Point Boulevard and City Line

Single-lane eastbound will be closed Monday to Thursday from 10 am to 2 pm and from 11 pm to 5 am next morning, Friday from 10 am to 2 pm and from 11 pm to 7 am next morning. Saturday from 11 pm to 11 am next morning. Double-lane eastbound will be closed Monday to Friday from 1 am to 5 am, Saturday from 1 am to 7 am, and Sunday from 2 am to 9 am. Single-lane westbound will be closed Monday to Thursday from 10 am to 3 pm and from 11 pm to 5 am next morning, Friday from 10 am to 3 pm and from 10 pm to 6 am next morning, and Saturday from 10 pm to 11 am next morning. Double-lane westbound will be closed Monday to Friday from 1 am to 5 am, Saturday from 1 am to 6 am, and Sunday from 2 am to 9 am. Intermittent 15-minute full closure in one direction at a time may occur Monday to Saturday between 2 am and 5 am except holidays and embargo days for maximum of five nights. On and Off-Ramps within this segment will be reduced to 14 feet Monday to Saturday from 10 pm to 5 am next morning. These closures are necessary to facilitate installation of ATDM and ITS equipment and will continue through September 27, 2024.

Nassau Expressway between Cross Bay Boulevard Entrance Ramp and Exit 2N

Single-lane eastbound will be closed Monday to Thursday from 10 am to 3 pm and 9 pm to 5 am next morning, Friday from 10 pm to 7 am next morning, and Saturday from 10 pm to 7 am next morning. Double-lane eastbound will be closed Monday to Friday from 12:01 am to 5 am, Saturday from 12:01 am to 7 am, and Sunday from 12:01 am to 7 am. Eastbound Exit Ramp 2S will be closed Monday to Thursday from 11 pm to 7 am next morning, Friday from 11 pm to 7 am next morning, and Saturday from 11 pm to 7 am next morning. These closures are necessary to facilitate JFK Redevelopment Program and will continue through December 31, 2025.

12 Street between Broadway and 31 Avenue

This street will be closed from 9 am to 4 pm Friday, and 8 am to 4 pm Saturday through 6/19/24 for 36” gas transmission main installation.

12 Street between 33 Avenue and Broadway

This street will be closed from 9 am to 4 pm Friday, and 8 am to 4 pm Saturday through 6/19/24 for 36” gas transmission main installation.

27th Street between 41st Avenue and Queens Plaza North

This street will be closed from 9 am to 4 pm Friday through 5/4/24 for installation of water service.

29 Street between 23 Road and 24 Avenue

This street will be closed from 9 am to 2 pm Monday to Friday through 4/29/24 for lifting flagpole to front of building for installation.

30th Street between 30th Avenue and Newtown Avenue

This street will be closed from 8 am to pm Saturday, and 9 am to 6 pm Sunday through 5/10/24 to facilitate crane operation.

37th Avenue between College Point Boulevard and Bud Place

This street will be closed from 9 am to 4 pm Friday, and 8 am to 4 pm Saturday through 5/8/24 to facilitate crane operation.

44 Street between 34 Avenue and 35 Avenue

This street will be closed from 9 am to 4 pm Friday through 6/28/24 for concrete pouring.

45 Street between 34 Avenue and Northern Boulevard

This street will be closed from 9 am to 4 pm Friday through 6/28//24 for concrete pouring.

49th Street between 50th Avenue and 48th Avenue

This street will be closed 24/7 through 6/23/24 to facilitate crane operation.

49th Avenue between Center Boulevard and 5th Street

This street will be closed from 7:30 am to 9 pm Saturday and Sunday through 5/5/24 to facilitate crane operation.

66th Avenue between Queens Boulevard and 99th Street

This street will be closed from 9 am to 4 pm Friday, and 8 am to 4 pm Saturday through 5/12/24 for new building construction, concrete pouring operations.

78 Avenue between Austin Street and Kew Forest Lane

This street will be closed from 9 am o 4 pm Friday through 4/30/24 for concrete pump, material delivery, boom operations.

97 Avenue between Sutphin Boulevard and Waltham Street

This street will be closed from 9 am to 4 pm Friday through 5/1/24 for concrete pump to erect new building.

148th Street between 95th Avenue and 94th Avenue

This street will be closed from 7 am to 6 pm Monday to Friday through 4/30/24 for use of crane, boom/concrete pump to be placed on roadway for new building.

149th Avenue between Redding Street and Cross Bay Boulevard (Albert Road)

This street will be closed from 9 pm to 5 am weeknights through 4/28/24 to facilitate crane operation.

Penrod Street between 108th Street and Horace Harding Expressway

This street will be closed from 8 am to 4 pm Saturday through 6/30/24 for DEP contract PS-277 108th Street pump station reconstruction.

Britton Avenue between Broadway and Layton Street

This street will be closed from 9 am to 4 pm Friday through 4/30/24 to facilitate crane operation.

Prince Street between Linneaus Place and 35th Avenue

This street will be closed from 9 am to 4 pm Friday through 5/1/24 to facilitate crane operation.


Staten Island

Tompkins Avenue Bridge over Greenfield Avenue

Single-lane and parking on the east side of the bridge will be closed Monday to Friday from 7 am to 3:30 pm through May 17, 2024, to facilitate bridge rehabilitation. Two-way traffic will be maintained at all times.

Iona Street between Father Capodanno Boulevard and Quincy Avenue

This street will be closed from 7 am to 6 pm Monday to Friday through 6/12/24 for full roadway closure.

 